Hours spent tell you what a project has cost. They don’t tell you what it has earned. Here is how to measure both, while there is still time to act on the answer.

6 min read · Updated November 2026

Why hours alone mislead

On an hourly project, profitability is simple: every hour logged is billed at the agreed rate. On a fixed-fee project the fee doesn’t move. What moves is how much work it takes to earn it.

So the number most practices watch, hours logged against hours budgeted, tells half the story. A project that has used 70% of its hours sounds fine. If it is only 55% complete, it isn’t. Profitability on a fixed fee comes from comparing two things: what the work has cost, and how much of the fee the work has earned.

That takes five numbers: the fee, the hours it was sold on, progress, the cost of an hour, and your overhead. The steps below work through each one, then put them together in a worked example.

Step 1: Measure progress by weight, not by count

Progress is the number everything else depends on, and the easiest one to get wrong. Asking the project architect “how far through are we?” gives you a feeling. Counting finished tasks gives you a number that flatters, because small tasks finish quickly.

Instead, weight each task by the hours it was sold for. A task worth 80 hours that is a quarter done counts for more than a 10-hour task that is finished.

TaskSold hoursCompleteHours of work done
Site analysis10100%10
Construction documentation set8025%20
Project9033%30

Averaging the two percentages says the project is 62.5% complete. Weighting by hours says 30 of 90 hours of work are done: 33%. The weighted figure is the honest one.

Progress should come from the work, not from the hours. A task that has used all of its hours isn’t complete until its drawings are.

Step 2: Work out what the project has earned

Earned fee is the fee multiplied by progress.

A $60,000 project that is 55% complete has earned $33,000, regardless of what has been invoiced and how many hours have been logged.

Earned fee less what you have already invoiced is work in progress: work done but not yet billed. When invoicing falls behind progress, the practice is funding the client’s project. Check it every month, and invoice the difference.

Step 3: Compare hours used with work done

Divide the hours used by the hours sold, and set that percentage beside progress.

  • Hours used below progress: the project is ahead of its budget.
  • About the same: it is on track.
  • Hours used ahead of progress: it is using its fee faster than it is completing the work.

To see where it is heading, project the hours at completion: hours used divided by progress. 168 hours at 55% complete projects to about 305 hours. If the fee was sold on 240, the project is heading about 65 hours over.

This assumes the rest of the work goes at the same pace as the work so far. Treat it as a warning, not a forecast. It is most useful early, while there is still enough fee left to change course.

Step 4: Cost the hours properly

An hour of a staff member’s time costs the practice more than their hourly wage. Start with the annual cost of employing them: salary, superannuation, payroll tax where it applies, workers’ compensation insurance and any other on-costs. Then divide by the hours they actually spend on project work in a year, not by 52 weeks of full-time hours. Annual leave, public holidays, personal leave, training and practice administration all come out first.

For example, a salary of $115,000 with $23,000 of on-costs costs $138,000 a year. If that person spends 1,450 hours a year on project work, each project hour costs about $95.

Work this out for each person, or at least for each role. A project staffed mainly by directors costs far more per hour than one staffed by graduates, and the margin should show it.

Step 5: Add overhead

Rent, software, insurance, accounting, marketing, and the time of anyone who doesn’t work on projects all have to be paid for by project work. Add up a month’s overhead and divide it by the project hours logged across the practice that month. That is your overhead per project hour.

For example, $29,700 of overhead in a month when the practice logged 540 project hours is $55 an hour.

Using each month’s actual hours, rather than a target, means overhead per hour rises in a quiet month. That is the point: quiet months are expensive, and the projects worked on in them carry more of the practice’s costs.

Worked example

A fixed fee of $60,000 for design development and construction documentation, sold on 240 hours. Staff cost $95 an hour on average, and overhead runs at $55 an hour. Four months in:

Fee$60,000
Hours sold240
Hours used168 (70%)
Progress, weighted by hours55%
Earned fee$33,000
Invoiced to date$24,000
Ready to invoice$9,000
Staff cost (168 hours at $95)$15,960
Margin before overhead$17,040 (52% of earned)
Overhead (168 hours at $55)$9,240
Net margin to date$7,800 (24% of earned)

So far the project is still making money. But it has used 70% of its hours for 55% of the work, and at this pace it finishes at about 305 hours. At $150 an hour of staff cost and overhead, that is $45,750 against a $60,000 fee: a net margin of about 24%. Finished on its 240 hours, it would have cost $36,000, a margin of 40%.

The 65 extra hours would cost the practice $9,750 of profit. Four months in, most of that can still be saved. And the $9,000 ready to invoice should go out this month.

Act while there’s still fee left

These numbers are only useful if they are current and someone acts on them. Review them monthly at the least, and weekly on projects that are already drifting. When a project is using its fee faster than it is completing the work:

  • Check the scope first. Hours often run over because the scope grew. If it did, that is a variation, and it should be priced.
  • Re-estimate what is left, with the people doing the work, row by row.
  • Change the allocation. Someone more experienced may finish the remaining work in fewer hours; someone less senior may do it at a lower cost.
  • Feed it back. Record which rows overran and price them better next time. Our fee proposal template shows how to price from the drawing list up so you can.

Video tutorials

See TrackerPlus at work, step by step.

Short videos for owners, staff, clients and consultants, from the first fee proposal to the final invoice.

Free for up to 2 people. Upgrade when you outgrow it.
Next in TrackerPlusBilling & Profitability

The same method, built into TrackerPlus.