Kestrel Property Partners — Project update 30 October 2026
Please find below the current position on each project. Items waiting on your team are listed first under each project.
Kestrel Lane
Email summary
7 emails in the period with Fiona Hargreaves. Main topics: board decision on facade option 2 before tender award.
External chat summary
6 messages in the client channel (3 from the client). The main concern raised: tender queries unanswered for a week with the close approaching.
Combined summary
Tender documentation is complete and both tenderers have priced Addendum 2. The cost report puts the facade 9% over budget; three value-management options were issued and option 2 (about $186k saving, no change to the street elevation) is recommended for the board on Thursday. The team logged 154.3 hours in the period.
Outstanding items
Waiting on Ember Fire Engineering
- Fire engineering report revision C for the stair pressurisation change — open 7 days (since 23 Oct)
Waiting on Kestrel Property Partners
- Board decision on facade option 2 before tender award — open 0 days (since 30 Oct)
Closed since last update
- Monthly cost report for the investment committee
- Facade value-management options with cost and programme impact