Architecture fee proposal template, with a worked example

What to put in an architecture fee proposal, section by section, and how to price it from the drawing list up, so the hours you sell are hours you can actually deliver.

6 min read · Updated November 2026

What a fee proposal has to do

A fee proposal does three jobs at once. It tells the client what they are buying. It sets the fee. And, less obviously, it sets the hours your practice has to deliver the work in. The first two get most of the attention. The third decides whether the project makes money.

A proposal priced as a lump sum, with no hours behind it, leaves nobody able to say halfway through documentation whether the project is on track. A proposal priced from a drawing list, with hours against every row, becomes the budget the team works to.

The template below is built that way: scope first, then hours, then the fee.

The fee proposal template, section by section

Use these sections in this order, as a checklist or a template. Most of them carry over from project to project; the scope and fee sections are written fresh each time.

  1. Introduction Who you are, in two or three sentences, and why the practice suits this project. Keep it short; the client has usually met you already.
  2. Project understanding The site, the brief as you understand it, the construction budget the client has given you, and the constraints you already know about: a heritage overlay, planning controls, a fixed move-in date. Writing this down shows you listened, and it records what the fee is based on.
  3. Scope of services by stage One heading per stage, for example concept design, design development, planning approval, construction documentation, tender and contract administration. Under each, what you will do and what you will hand over.
  4. Deliverables The drawing list for each stage: which drawings, at what scale, how many sheets. Most proposals leave this out. It is the part that makes the fee defensible.
  5. Fee and fee basis The fee for each stage, the total, and how it is calculated: a fixed fee, hourly rates with an estimate, or a percentage of the construction cost. Say whether the amounts include GST.
  6. Exclusions What the fee does not cover. The usual candidates: consultants’ fees (structural, civil, building surveyor, energy assessment, land surveyor), authority and application fees, specialist reports, more design options than the number stated, and redesign after approval.
  7. Assumptions The number of design options, meetings and revisions in each stage, how quickly the client will respond, and who supplies the survey. Each assumption is a line you can point to when the scope changes.
  8. Additional services and variations Your hourly rates by role, and how a variation is agreed: in writing, with an estimate, before the work starts.
  9. Invoicing and payment terms When you invoice, monthly on progress or at the end of each stage, and when payment is due.
  10. Acceptance How long the proposal is valid, and how the client accepts it: a signature, or written acceptance by email, against a specific version of the proposal.

Stage names differ between states and between practices. Use the names your clients and your contracts use. If you work under a standard client–architect agreement, make the proposal’s stages and terms match it.

Price from the drawing list up

For each stage, list the drawings you expect to issue. Estimate the hours each drawing needs and multiply by the number of sheets. Then add rows for the work that isn’t a drawing: consultant coordination, meetings, specification writing, authority submissions. The stage’s hours are the sum of its rows, and the stage fee is those hours at your charge-out rate.

This takes longer than writing a lump sum. It is also the only way to know later whether the hours were enough. Each row is a small estimate you can check. When a project runs over, you can see which rows ran over, and price the next proposal better.

Two habits make the estimates more reliable:

  • Estimate from your own records, not from memory. If your team has logged time against similar drawings on past projects, that number beats any guess.
  • Price the drawings you will actually issue. If a detail sheet has always become three sheets by the end, price three.

Fee proposal example: a house alteration and addition

A sample fee proposal: alterations and additions to a two-storey house, with a construction budget of $850,000. The practice charges $200 an hour. The figures are illustrative and exclude GST.

Construction documentation, from the drawing list
RowScaleSheetsHours a sheetHours
Site and demolition plans1:2002510
Floor plans1:5031030
Roof plan1:100144
Elevations1:1002816
Sections1:502816
Construction details1:5, 1:103618
Wet areas and joinery1:202510
Door, window and finishes schedules—166
Consultant coordination and specification———10
Construction documentation16120

At $200 an hour, construction documentation is 120 hours and $24,000.

Every stage, on the same basis
StageHoursFee
Concept design40$8,000
Design development50$10,000
Planning approval45$9,000
Construction documentation120$24,000
Tender and contractor selection15$3,000
Contract administration70$14,000
Total340$68,000

Contract administration depends on the builder’s programme more than on yours. Rather than an open-ended fixed fee, consider pricing it as a set number of site visits and meetings, with more at your hourly rates.

Check the fee three ways

Before the proposal goes out, test the total against three things.

  1. Hours. Do 340 hours look right for this house, compared with similar projects you have delivered? If your records say the last two took 400 hours each, the proposal is short before it starts.
  2. Percentage of construction cost. $68,000 is 8.0% of a $850,000 budget. Compare that with what your practice has charged, and been paid, on similar work.
  3. The effective hourly rate. If the client negotiates the fee down to $60,000 without reducing the scope, the 340 hours are now worth about $176 an hour. Decide before the meeting whether you can accept that, or which rows of scope come out instead.

The third check matters most in practice. When a fee is cut, cut scope with it, row by row, so the hours still match the work you have promised.

Plan for variations before they happen

Clients change their minds. That is normal, and a fee proposal should expect it. Three things make a variation straightforward:

  • The assumptions section says what is included, so a change can be recognised as a change.
  • Hourly rates by role are already agreed, so a variation can be estimated quickly.
  • Every version of the proposal is kept. When a variation is accepted, issue a new version with the added rows, so the scope the client accepted at each point stays on record.

Raise the variation before doing the work. Work done first and priced later is rarely paid in full.

Fee proposal checklist before you send

Run through this list before the proposal leaves the office.

Scope

  • Every stage has a heading, a description of the work and a list of what is handed over.
  • Stage names match the agreement you will sign with the client.
  • The drawing list shows drawing, scale and sheet count for each stage.

Hours and fee

  • Every row has hours, and every stage total is the sum of its rows.
  • Row estimates come from logged time on past projects where you have it.
  • Non-drawing work is priced: coordination, meetings, specification, submissions.
  • The total has been checked against similar past projects in hours.
  • The total has been checked as a percentage of the construction budget.
  • You know the lowest effective hourly rate you will accept, and which rows come out if the fee is cut.
  • The proposal states whether amounts include tax.

Protection

  • Exclusions are listed, including consultants and authority fees.
  • Assumptions state the number of options, meetings and revisions.
  • Hourly rates by role are included for variations.
  • Contract administration is defined by visits and meetings, not left open.

Admin

  • Invoicing timing and payment terms are stated.
  • The validity period and the way to accept are clear.
  • The version number is on the document, and a copy is saved.

After the client accepts

The accepted proposal is the project’s budget. The 120 hours for construction documentation are the hours the team has to deliver it in, row by row. Carry the rows into the project as tasks, give each one to a person, and log time against them.

Then progress can be measured against what was sold, which is the subject of our guide to measuring profitability on a fixed-fee project. And the same hours tell you whether the team has room for the work, which is covered in planning staff workload.

Where can I get an architecture fee proposal template?

The template is built into TrackerPlus. You keep your standard sections as templates, price each stage from drawing rows and hours, and send the client a branded PDF. Each version is kept, so you can always see which one the client accepted.

Should an architecture fee be fixed, hourly or a percentage of construction cost?

Any of the three can work, provided there are hours underneath it. Price the drawing list in hours first, then present the result in whichever basis your client and contract expect. In the worked example, the $68,000 fixed fee is also 340 hours and 8.0% of construction cost.

Does this template work for interior design or drafting studios?

Yes. The sections stay the same and only the deliverables change. An interior design proposal might list joinery, finishes and furniture drawings. A drafting studio might price documentation sheets only. The method of pricing each row in hours carries over unchanged.

Can I try building fee proposals in TrackerPlus for free?

The free plan covers up to two people with no time limit. Starting it needs card verification, and nothing is charged.

Video tutorials

See TrackerPlus at work, step by step.

Short videos for owners, staff, clients and consultants, from the first fee proposal to the final invoice.

Free for up to 2 people. Upgrade when you outgrow it.
Next in TrackerPlusProjects & Fees

The same method, built into TrackerPlus.