Architecture fee proposal template, with a worked example
What to put in an architecture fee proposal, section by section, and how to price it from the drawing list up, so the hours you sell are hours you can actually deliver.
What a fee proposal has to do
A fee proposal does three jobs at once. It tells the client what they are buying. It sets the fee. And, less obviously, it sets the hours your practice has to deliver the work in. The first two get most of the attention. The third decides whether the project makes money.
A proposal priced as a lump sum, with no hours behind it, leaves nobody able to say halfway through documentation whether the project is on track. A proposal priced from a drawing list, with hours against every row, becomes the budget the team works to.
The template below is built that way: scope first, then hours, then the fee.
The fee proposal template, section by section
Use these sections in this order, as a checklist or a template. Most of them carry over from project to project; the scope and fee sections are written fresh each time.
- Introduction Who you are, in two or three sentences, and why the practice suits this project. Keep it short; the client has usually met you already.
- Project understanding The site, the brief as you understand it, the construction budget the client has given you, and the constraints you already know about: a heritage overlay, planning controls, a fixed move-in date. Writing this down shows you listened, and it records what the fee is based on.
- Scope of services by stage One heading per stage, for example concept design, design development, planning approval, construction documentation, tender and contract administration. Under each, what you will do and what you will hand over.
- Deliverables The drawing list for each stage: which drawings, at what scale, how many sheets. Most proposals leave this out. It is the part that makes the fee defensible.
- Fee and fee basis The fee for each stage, the total, and how it is calculated: a fixed fee, hourly rates with an estimate, or a percentage of the construction cost. Say whether the amounts include GST.
- Exclusions What the fee does not cover. The usual candidates: consultants’ fees (structural, civil, building surveyor, energy assessment, land surveyor), authority and application fees, specialist reports, more design options than the number stated, and redesign after approval.
- Assumptions The number of design options, meetings and revisions in each stage, how quickly the client will respond, and who supplies the survey. Each assumption is a line you can point to when the scope changes.
- Additional services and variations Your hourly rates by role, and how a variation is agreed: in writing, with an estimate, before the work starts.
- Invoicing and payment terms When you invoice, monthly on progress or at the end of each stage, and when payment is due.
- Acceptance How long the proposal is valid, and how the client accepts it: a signature, or written acceptance by email, against a specific version of the proposal.
Stage names differ between states and between practices. Use the names your clients and your contracts use. If you work under a standard client–architect agreement, make the proposal’s stages and terms match it.
Price from the drawing list up
For each stage, list the drawings you expect to issue. Estimate the hours each drawing needs and multiply by the number of sheets. Then add rows for the work that isn’t a drawing: consultant coordination, meetings, specification writing, authority submissions. The stage’s hours are the sum of its rows, and the stage fee is those hours at your charge-out rate.
This takes longer than writing a lump sum. It is also the only way to know later whether the hours were enough. Each row is a small estimate you can check. When a project runs over, you can see which rows ran over, and price the next proposal better.
Two habits make the estimates more reliable:
- Estimate from your own records, not from memory. If your team has logged time against similar drawings on past projects, that number beats any guess.
- Price the drawings you will actually issue. If a detail sheet has always become three sheets by the end, price three.
Fee proposal example: a house alteration and addition
A sample fee proposal: alterations and additions to a two-storey house, with a construction budget of $850,000. The practice charges $200 an hour. The figures are illustrative and exclude GST.
| Row | Scale | Sheets | Hours a sheet | Hours |
|---|---|---|---|---|
| Site and demolition plans | 1:200 | 2 | 5 | 10 |
| Floor plans | 1:50 | 3 | 10 | 30 |
| Roof plan | 1:100 | 1 | 4 | 4 |
| Elevations | 1:100 | 2 | 8 | 16 |
| Sections | 1:50 | 2 | 8 | 16 |
| Construction details | 1:5, 1:10 | 3 | 6 | 18 |
| Wet areas and joinery | 1:20 | 2 | 5 | 10 |
| Door, window and finishes schedules | — | 1 | 6 | 6 |
| Consultant coordination and specification | — | — | — | 10 |
| Construction documentation | 16 | 120 |
At $200 an hour, construction documentation is 120 hours and $24,000.
| Stage | Hours | Fee |
|---|---|---|
| Concept design | 40 | $8,000 |
| Design development | 50 | $10,000 |
| Planning approval | 45 | $9,000 |
| Construction documentation | 120 | $24,000 |
| Tender and contractor selection | 15 | $3,000 |
| Contract administration | 70 | $14,000 |
| Total | 340 | $68,000 |
Contract administration depends on the builder’s programme more than on yours. Rather than an open-ended fixed fee, consider pricing it as a set number of site visits and meetings, with more at your hourly rates.
Check the fee three ways
Before the proposal goes out, test the total against three things.
- Hours. Do 340 hours look right for this house, compared with similar projects you have delivered? If your records say the last two took 400 hours each, the proposal is short before it starts.
- Percentage of construction cost. $68,000 is 8.0% of a $850,000 budget. Compare that with what your practice has charged, and been paid, on similar work.
- The effective hourly rate. If the client negotiates the fee down to $60,000 without reducing the scope, the 340 hours are now worth about $176 an hour. Decide before the meeting whether you can accept that, or which rows of scope come out instead.
The third check matters most in practice. When a fee is cut, cut scope with it, row by row, so the hours still match the work you have promised.
Plan for variations before they happen
Clients change their minds. That is normal, and a fee proposal should expect it. Three things make a variation straightforward:
- The assumptions section says what is included, so a change can be recognised as a change.
- Hourly rates by role are already agreed, so a variation can be estimated quickly.
- Every version of the proposal is kept. When a variation is accepted, issue a new version with the added rows, so the scope the client accepted at each point stays on record.
Raise the variation before doing the work. Work done first and priced later is rarely paid in full.
Fee proposal checklist before you send
Run through this list before the proposal leaves the office.
Scope
- Every stage has a heading, a description of the work and a list of what is handed over.
- Stage names match the agreement you will sign with the client.
- The drawing list shows drawing, scale and sheet count for each stage.
Hours and fee
- Every row has hours, and every stage total is the sum of its rows.
- Row estimates come from logged time on past projects where you have it.
- Non-drawing work is priced: coordination, meetings, specification, submissions.
- The total has been checked against similar past projects in hours.
- The total has been checked as a percentage of the construction budget.
- You know the lowest effective hourly rate you will accept, and which rows come out if the fee is cut.
- The proposal states whether amounts include tax.
Protection
- Exclusions are listed, including consultants and authority fees.
- Assumptions state the number of options, meetings and revisions.
- Hourly rates by role are included for variations.
- Contract administration is defined by visits and meetings, not left open.
Admin
- Invoicing timing and payment terms are stated.
- The validity period and the way to accept are clear.
- The version number is on the document, and a copy is saved.
After the client accepts
The accepted proposal is the project’s budget. The 120 hours for construction documentation are the hours the team has to deliver it in, row by row. Carry the rows into the project as tasks, give each one to a person, and log time against them.
Then progress can be measured against what was sold, which is the subject of our guide to measuring profitability on a fixed-fee project. And the same hours tell you whether the team has room for the work, which is covered in planning staff workload.